VA contract 36C25622P1059: Chiller repair
Red River Pump Specialists Inc held VA contract 36C25622P1059 for chiller repair in Pineville, LA. It started on Jun 17, 2022, and $15,667 has been obligated so far. The VA received a single offer. This contract ended on Aug 31, 2022.
| Contract number | 36C25622P1059 |
|---|---|
| Contract holder | Red River Pump Specialists Inc |
| Holder UEI | DAYKCJ1ZXZN7 |
| Description | Chiller repair |
| Location | Pineville, LA |
| Contracting office | VA Network Contract Office 16 (36C256) |
| Obligated to date | $15,667 |
| Start date | Jun 17, 2022 |
| Current end date | Aug 31, 2022 |
| Offers received | 1 |
| Set-aside | No set-aside |
| Competition | Competed (simplified acquisition) |
| Kind of work | Maintenance repair |
| Official record | USAspending.gov |
Details come from the official record on USAspending.gov. Confirm them there before relying on them. See something wrong in our summary? Report a problem with this contract.
Other VA HVAC and plumbing contracts in Pineville, LA
- 36C25626P0523: Air emission testing for three natural gas generators, $32,760, ended Aug 31, 2026
- 36C25626P0490: Compressor replacement, $219,970, ended May 1, 2026
- 36C25625C0023: 500T chiller rental, $1.2 million, ends Mar 2, 2027
- 36C25624P1373: Base contract to perform inspection, tuning, testing, calibrating, and adjustments of burners and boiler plant controls, $18,277, ended Aug 29, 2025
- 36C25624C0069: Emergency chiller #2 repairs, $2.2 million, ended Mar 2, 2025
- 36C25624C0020: Project 502-21-110 (construction) - replace chiller #3, $1.6 million, ended Oct 12, 2025
- 36C25624P0336: Installation of steam condensate LINER-502, $98,755, ended Jun 30, 2024
- 36C25623P0877: Taco rotator replacement pump services, $17,848, ended Sep 30, 2023
Other VA contracts held by Red River Pump Specialists Inc
- 36C25623P0877: Taco rotator replacement pump services, $17,848, ended Sep 30, 2023