VA contract 36C26220P0494: HVAC system upgrade west la VA hospital 11301 wilshire BLVD
Johnsondanforth, Inc held VA contract 36C26220P0494 for HVAC system upgrade west la VA hospital 11301 wilshire BLVD in Little Rock, AR. It started on Jan 31, 2020, and $148,410 has been obligated so far. The VA received a single bid. This contract ended on Mar 31, 2020.
| Contract number | 36C26220P0494 |
|---|---|
| Contract holder | Johnsondanforth, Inc |
| Holder UEI | TFC8L4UHKE15 |
| Description | HVAC system upgrade west la VA hospital 11301 wilshire BLVD |
| Location | Little Rock, AR |
| Contracting office | VA Network Contract Office 22 (36C262) |
| Obligated to date | $148,410 |
| Start date | Jan 31, 2020 |
| Current end date | Mar 31, 2020 |
| Bids received | 1 |
| Set-aside | No set-aside |
| Competition | Not competed |
| Kind of work | Equipment |
| Official record | USAspending.gov |
Details come from the official record on USAspending.gov. Confirm them there before relying on them. See something wrong in our summary? Report a problem with this contract.
Other VA HVAC and plumbing contracts in Little Rock, AR
- 36C25626P0740: Air flow and pressure testing - EO 14398, $101,424, ends Jun 9, 2027
- 36C25625N0522: Air flow-pressure balance & testing services, $45,867, ended Feb 14, 2026
- 36C25624C0036: Replace AHUS 47, 48, 48B & 22, $4.2 million, ends Jun 13, 2027
- 36C25624N0588: Perform air flow/pressure balance and testing services, $45,867, ended Feb 14, 2025
- 36C25624P0307: Water boiler maintenance, $26,800, ends Nov 30, 2026
- 36C25624P0087: Emergency replacement of boiler tubes, $178,146, ended Dec 22, 2023
- 36C25623N0549: Air flow/pressure balance & testing services, $45,867, ended Feb 14, 2024
- 36C25622N0457: Air flow/pressure balance & testing services, $45,867, ended Feb 14, 2023
Other VA contracts held by Johnsondanforth, Inc
- 36C26226P1776: Replace refrigerant in chillers, $35,930, ends Jan 10, 2027
- 36C26226P1170: Emergency AC repair, $39,055, ended Aug 6, 2026
- 36C25726P0529: NTX HVAC maintenance and repair, $682,885, ends May 31, 2027
- 36C26225P1962: Emergency steam regulator replacement, $15,880, ended Mar 13, 2025
- 36C26224P1547: Chiller replacement, $94,999, ended Jul 31, 2024
- 36C26224P1507: Emergency condenser pump replacement, $29,500, ended Jun 30, 2024
- 36C26224P1670: Emergency pipe repair, $25,975, ended Oct 23, 2024
- 36C26224P1042: Fire pump/motor replacement, $97,320, ended Jun 30, 2024