VA contract VA24816C0182: Construction improve mechanical utilities - phase 4
Sergents Mechanical Systems Inc held VA contract VA24816C0182 for construction improve mechanical utilities - phase 4 in Gainesville, FL. It started on Sep 28, 2016, and $5.0 million has been obligated so far. The VA received 3 bids. This contract ended on Dec 31, 2020.
| Contract number | VA24816C0182 |
|---|---|
| Solicitation number | VA248-16-R-0467 |
| Contract holder | Sergents Mechanical Systems Inc |
| Holder UEI | VNPDQR925EH3 |
| Description | Construction improve mechanical utilities - phase 4 |
| Location | Gainesville, FL |
| Contracting office | VA Network Contract Office 8 (36C248) |
| Obligated to date | $5.0 million |
| Start date | Sep 28, 2016 |
| Current end date | Dec 31, 2020 |
| Bids received | 3 |
| Set-aside | Service-disabled veteran-owned small business (SDVOSB) set-aside |
| Competition | Competed among eligible businesses (set-aside) |
| Kind of work | Construction |
| Official record | USAspending.gov |
Details come from the official record on USAspending.gov. Confirm them there before relying on them. See something wrong in our summary? Report a problem with this contract.
Other VA HVAC and plumbing contracts in Gainesville, FL
- 36C24824P2012: Boiler room valves replacement, $247,360, ended Oct 1, 2024
- 36C24824P0995: Chiller 5 rebuild, $65,788, ended Jul 31, 2024
- 36C24824P0832: Rebuild chiller and install VFD, $501,212, ended Mar 15, 2025
- 36C24824P0893: Air handling unit testing, $9,500, ended May 14, 2024
- 36C24824P0682: Emergency boiler plant sump repair, $222,486, ended Sep 30, 2024
- 36C24824P0207: Emergency- rewire boiler safety devices, $31,472, ended May 1, 2024
- 36C24823P2325: Emergency boiler repair, $99,699, ended Jan 31, 2024
- 36C24823P0881: Chiller plant maintenance, $267,776, ends Jun 14, 2027
Other VA contracts held by Sergents Mechanical Systems Inc
- 36C25723C0002: Replace cooling towers BLDG. 18, $869,735, ended Feb 16, 2024
- 36C25723C0016: Replace AHUS covid wards 6J-6K temple, $3.0 million, ended Jul 7, 2025
- 36C25621C0021: Project #502-19-103 replace BLDG 7 AHUS, $3.5 million, ended Jan 31, 2023
- 36C26118C0129: Backup cooling to critical care, $2.3 million, ended Feb 17, 2020
- 36C25818C0094: B26 HVAC replacement, $4.6 million, ended Jun 23, 2023
- VA24217C0102: Replace AHU 3 and AHU 8, $2.7 million, ended Dec 31, 2019
- VA24817C0026: Replace AC and environmental controls, $3.8 million, ended Dec 1, 2021
- VA24615C0009: Replace air handling unit Durham VAMC, $2.7 million, ended Oct 23, 2016