Richard Group LLC held VA contract 36C25220C0201 for 537-18-301B. legionella corrections in Chicago, IL. It started on Sep 30, 2020, and $2.0 million has been obligated so far. The VA received 2 offers. This contract ended on Sep 25, 2022.
| Contract number | 36C25220C0201 |
|---|---|
| Solicitation number | 36C25220R0053 |
| Contract holder | Richard Group LLC |
| Holder UEI | QST7A5N63TL4 |
| Description | 537-18-301B. legionella corrections |
| Location | Chicago, IL |
| Contracting office | VA Network Contract Office 12 (36C252) |
| Obligated to date | $2.0 million |
| Start date | Sep 30, 2020 |
| Current end date | Sep 25, 2022 |
| Offers received | 2 |
| Set-aside | Service-disabled veteran-owned small business (SDVOSB) set-aside |
| Competition | Competed among eligible businesses (set-aside) |
| Kind of work | Construction |
| Official record | USAspending.gov |
Details come from the official record on USAspending.gov. Confirm them there before relying on them. See something wrong in our summary? Report a problem with this contract.
Other VA HVAC and plumbing contracts in Chicago, IL
- 36C25226P0534: Fire pump repacking - peerless fire pump, bed tower at jesse brown VAMC, $6,701, ends Oct 22, 2026
- 36C25226P0577: Emergency chiller chilled water repair service, $35,845, ended Sep 20, 2026
- 36C25226P0511: Air handler refurbishment for the jesse brown VAMC, Chicago, il, $231,544, ends Nov 30, 2026
- 36C25226C0042: Requirement construction project 537-24-500, facility cooling upgrades, $4.4 million, ends Aug 9, 2027
- 36C25226P0407: Ntp, $147,690, ends Oct 22, 2026
- 36C25225C0037: Vmu equipment tie in, $242,650, ended Dec 15, 2025
- 36C25225P0296: Dialysis and reverse osmosis testing maintenance, $819,895, ends Feb 28, 2030
- 36C25225P0233: BASE+4 backflow preventer service contract at the jesse brown VA medical center (537), $41,820, ends Jan 31, 2030
Other VA contracts held by Richard Group LLC
- 36C25221C0108: Sealed bid award for project 695-19-104, replace fire sprinklers at the Milwaukee VA, $1.3 million, ended Sep 1, 2023
- 36C25221C0100: Project 585-20-111 low pressure steam riser at oscar g johnson VA medical center, iron mountain, mi, $1.1 million, ended Sep 26, 2022
- 36C25221P0323: Replacement of condenser pump at captain james a. lovell federal health care center north Chicago, $42,245, ended Mar 31, 2021
- 36C25220C0199: Ifb and contract for project 695-19-114, upgrade plumbing for legionella prevention, $8.8 million, ended Jun 8, 2026
- 36C25219C0136: Upgrade heat exchangers and replace perimeter heat at oscar g. johnson VA medical center, iron mountain, mi, $2.5 million, ended Oct 15, 2020
- 36C25219C0131: Upgrade AHU 10&11 construction at the oscar g johnson VA medical center, iron mountain, mi 49801, $1.4 million, ended Jan 23, 2020
- 36C25219C0045: Ot:igf:ot correct boiler safety deficiencies, $1.3 million, ended Nov 15, 2019
- 36C10X18P0195: The contractor shall provide all labor, supervision, tools, transportation, equipment, and materials necessary to remove and replace a total of one hundred fifty-four (154) high-efficiency heat pumps of brand name OR equal to section b heat pump data matrix (office setting) and digital ats/temperature sensors that are building automation and control network (bacnet) compatible. units shall be compatible with existing digital data controller (DDC) system and software (alerton building suite V2.6), $2.0 million, ended Sep 25, 2019